SAP PP Capacity Planning: CM01, CM21

The main function of capacity planning is to check the load at Work Center and do the capacity leveling i.e. balance the load at Work Center. It helps to calculate the production capacity based on the requirement of the product against the available capacity of the work center.

In this tutorial- you will learn,

How to check capacity loads

Capacity evaluation is used to analyze the load at Work Center, and you can see the load % (in step 2), available capacities and the requirements. You can also see the orders which have generated capacity requirements.

Step 1) From SAP easy access screen, open transaction CM01.

  1. Enter your manufacturing Plant for which you want to check capacity load.

Capacity Requirement Planning in SAP PP: CM01, CM21

After filling in all the fields, clickCapacity Requirement Planning in SAP PP: CM01, CM21 to go to the next screen.

Step 2) In this screen, the capacity situation at Work Center can be seen.

  1. Check the capacity requirement (generated from production orders), available capacity ( determined from Work Center master data) and capacity load % at the Work Center.

Capacity Requirement Planning in SAP PP: CM01, CM21

How to do Capacity Levelling

Capacity leveling is done through planning table, and you need to dispatch the orders to the Work Center in the sequence in which they are supposed to be processed at shop floor.

Step 1) From SAP easy access screen, open Transaction CM21

  1. Input the plant for which you want to level capacity

Capacity Requirement Planning in SAP PP: CM01, CM21

After filling in all the fields, click execute button on top to go to the next screen.

Step 2) In this screen, you can see orders pool at the bottom and Work Center pool at the upper half of the screen in the planning table.

  1. Check the several orders in the orders pool.
  1. Check the list of Work Centers in Work Centers pool.

Capacity Requirement Planning in SAP PP: CM01, CM21

Step 3) In the same screen of planning table, select the data as given below.

  1. Select one order from orders pool.
  1. Click on dispatch button to assign that order to the Work Center.

Capacity Requirement Planning in SAP PP: CM01, CM21

Step 4) In the same screen,

  1. Check the dispatched order in the Work Center pool. Similarly, you can dispatch the others orders to the Work Center pool which would shift adjacent to the previously dispatched orders.

Capacity Requirement Planning in SAP PP: CM01, CM21

This is how you can do the capacity leveling.