SAP - PP
Long Term Planning (LTP) Tutorial in SAP PP: MS31, MS02, MD61
Long term planning (Simulative MRP) is used to simulate the future demand and supply situation in...
The production version is the link between a product BOM (Bill of Material) and the process Routing. It determines which alternative BOM is used together with which routing to produce a material or plan a material.
There may be different production versions based on the lot sizes and validity dates.
For example, there may be different versions if you want to produce 1 – 100 liter of paint than 100 – 1000 liter of paint, as such the different composition of BOM may be required in both cases.
In order to create production version, perform the following steps-
Step 1) From SAP Easy access screen open transaction C223
After filling in all the fields, click
or press Enter to go to the next screen.
Step 2) In this screen,
Step 3) In this screen, you can see the messages regarding the validity of BOM and routing for the material.
Click
or press F3 from the keyboard to the previous screen.
Step 4) In this screen, you can see the test status is indicated by green color.
Click
to save the new version, the system will show message " Production version saved" at the lower left corner.
Troubleshooting
Long term planning (Simulative MRP) is used to simulate the future demand and supply situation in...
The main function of capacity planning is to check the load at Work Center and do the capacity...
There are two types of goods movement against production order which impacts the inventory of the...
$20.20 $9.99 for today 4.4 (105 ratings) Key Highlights of SAP PP Module PDF: 147+ pages in this...
What is Planned Independent Requirement(PIR)? Planned Independent Requirements (PIR) are used to...
Work center is an organization unit where manufacturing activities are performed. In other words,...